Hi
We currently have a 3PAR 8200 we have 4 disk shelves total including the controllers. We plan to add more disk 3 more disk shelves. Our current setup is
Disk Shelf 0 - SFF
Disk Shelf 1 - SFF
Disk Shelf 2 - SFF
Disk Shelf 3 - LFF
Looking at the cabling guide
https://support.hpe.com/hpsc/doc/public ... =c04830947 the LFF should be the last shelf in the stack. We plan to add three more SFF shelves, would this mean we need to move the LFF shelf to the bottom of the stack below the new shelves, or chain down from the LFF shelf and add new SFF shelves below it.